How to model a replacement mid-way through the assessment period
Purpose
Section titled “Purpose”Let a building product be replaced one or more times over the course of the assessment period, the normal, non-offset replacement cycle.
Prerequisites
Section titled “Prerequisites”The building product has been added to a construction in the building model.
- Find the building product in the building model tree.
- Set a lifespan (RSL) in years, see How to set lifespans.
- Leave offset start empty: the replacement then happens automatically every time the lifespan runs out, starting from the project’s beginning.
Result
Section titled “Result”The number of replacements in module B4 is calculated as assessment period ÷ lifespan (rounded down), spread evenly across the whole period, not just once mid-way.
See also
Section titled “See also”- How to set lifespans
- B5 Renovation as a life cycle module: if the replacement should be registered as a renovation action in its own right