Skip to content
Support
Machine-translated from Danish

How to register the construction site's consumption

Register the construction site’s energy consumption during the construction phase (module A5).

You’re on Construction site.

  1. Under Energy supply (A5), click Add.
  2. Search for and choose an energy source (e.g. electricity or district heating) from the library.
  3. Enter Consumption: the total consumption over the entire construction period.
  4. If you have data for multiple years, add one row per year.

The contribution to module A5 is calculated as the energy source’s emission factor × consumption.

Electricity used for transporting waste, soil or materiel belongs under the transport sections, not under Energy supply. Keep the two types of electricity separate.