Machine-translated from Danish
How to register the construction site's consumption
Purpose
Section titled “Purpose”Register the construction site’s energy consumption during the construction phase (module A5).
Prerequisites
Section titled “Prerequisites”You’re on Construction site.
- Under Energy supply (A5), click Add.
- Search for and choose an energy source (e.g. electricity or district heating) from the library.
- Enter Consumption: the total consumption over the entire construction period.
- If you have data for multiple years, add one row per year.
Result
Section titled “Result”The contribution to module A5 is calculated as the energy source’s emission factor × consumption.
Electricity used for transporting waste, soil or materiel belongs under the transport sections, not under Energy supply. Keep the two types of electricity separate.