| Term (Danish) | English | Explanation |
|---|---|---|
| A1-A3 · Produktion | Product stage | The first three life cycle modules: raw material extraction, transport to the factory and manufacture of the building product. |
| A4 · Transport til byggeplads | Transport to construction site | The transport of the building product from factory to construction site. |
| A5 · Byggeproces | Construction/installation process | The construction work itself on site: installation, waste and the construction site’s energy consumption. See What belongs to the construction site (A5)?. |
| B1-B7 · Anvendelse | Use stage | The seven modules covering the building’s use phase, from ordinary use (B1) to operational energy (B6) and operational water (B7). |
| B4 · Udskiftning | Replacement | Replacement of a building product when its service life is shorter than the study period. See Reference period and service lives. |
| B5 · Renovering | Refurbishment | The module used to model a renovation as an event in the middle of the study period. |
| B6 · Driftsenergi | Operational energy use | The building’s energy consumption for operation (heating, cooling, ventilation and so on), calculated across each year of the study period. |
| Beregningsmodus | Calculation mode | Determines which life cycle modules are included in a calculation, different for BR23, BR25 and DGNB. |
| Betragtningsperiode | Reference study period | The number of years a calculation covers, typically 50 years. Used to determine when building products have to be replaced, and to distribute operational energy consumption. See Reference period and service lives. |
| Bibliotek | Library | Reusable content (building products, constructions) in three types: Official, Organisation and Personal, each with its own rules for who may view and edit. See The library types. |
| BR23 / BR25 | Danish Building Regulations 2023 / 2025 | The editions of the Danish building regulations that set climate requirements for new construction. |
| Byggevare | Building product | The smallest unit in the building model: a specific material or product, typically with an EPD or a generic emission value attached. |
| C1-C4 · Bortskaffelse | End-of-life stage | The four modules covering demolition, transport, waste processing and disposal at the end of the building’s service life. |
| Conformity check | Conformity check | The check the Danish Green Building Council performs on a submitted project version, against a locked copy of the calculation. See Conformity check. |
| DGNB | The Danish sustainability certification system, which has its own calculation mode with different module requirements than the building regulations. | |
| EN 15978 | The European standard for environmental assessment of buildings, in which the life cycle stages (A1-A3, A4-A5, B1-B7, C1-C4, D) are defined. The basis for LCAbyg’s entire calculation method. | |
| Egenproduktion | On-site energy generation | Energy the building produces itself, for example via solar panels. What is not used immediately is exported and accounted for in module D. |
| Emissionsdata | Emission data | The environmental impact attached to a building product: either as one combined factor or as one factor per year, which requires interpolation. See Emission data. |
| Energitillæg | Energy addition/supplement | A supplement from a BE18 calculation, which requires two energy framework calculations to be accounted for correctly. See Energy supplements from BE18. |
| EPD | Environmental Product Declaration | A documented, verified data set for a building product’s environmental impacts. |
| Ex-faserne | The designation for the life cycle modules used to model demolition of existing building products, separate from B4C. See Demolition of existing building products. | |
| Filformater | LCAbyg imports and exports via three formats: .lb5 (LCAbyg 5), Konto JSON and .lcabyg.json (LCAbyg). See The file formats. |
|
| Generisk data | Generic data | Average-based emission data, used when no specific EPD has been chosen. See Generic data vs. specific EPDs. |
| Grænseværdi | Limit value | The maximum climate impact (kg CO₂-eq/m²/year) a building may have in order to comply with §298. |
| GWP | Global Warming Potential | The most central environmental indicator in the climate requirement: the building’s contribution to global warming, measured in kg CO₂-eq. |
| Kladde | Draft | A library version that has not yet been published, and is therefore invisible to everyone else. See Published and draft. |
| Konstruktion | Construction | An assembly of building products (for example a wall build-up) that can be reused across building elements and projects. |
| LCA | Life Cycle Assessment | The systematic accounting of a building’s environmental impacts across its whole service life. |
| Levetid | Lifespan | The number of years a building product is expected to last before it has to be replaced (B4). See Reference period and service lives. |
| Låst data | Locked data | Data that cannot be edited directly in a project because it originates from a library. See Locked data. |
| Modul | Module | One of the standardised life cycle steps from EN 15978 (for example A1-A3 or B6), in which a calculation is accounted for. |
| Modul D | Benefits and loads beyond the system boundary: reuse, recovery and energy recovery. Reported separately and does not count towards the limit value. | |
| Nedrivning | Demolition | Disposal of an existing building or building product, modelled with the Ex stages and B4C. See Demolition of existing building products. |
| Opvarmet etageareal | Heated floor area | The building’s total heated area. Used for the energy framework calculation. Not to be confused with the reference area. |
| Organisationsrolle | Organisation role | The role a user has in the organisation (for example owner or member), separate from access to the individual project. See The two access systems. |
| Projektadgang | Project access | The three levels a user can have on a single project: project owner, editor or read-only. See Project owner, editor and read-only. |
| Publiceret | Published | The status a library version gets when it becomes visible to others than the creator. See Published and draft. |
| Referenceareal | Reference area | The area the limit value (kg CO₂-eq/m²/year) is calculated from, weighted according to §297 subsection 5. Not the same as heated floor area. |
| Renovering | Refurbishment | In LCAbyg this can mean three different things depending on the context. |
| Standardværdi | Standard value | A predefined emission value for technical installations, used when no specific data has been entered. |
| Særlige forhold | Special conditions | A category for impacts that do not fit into the ordinary building model. See Special conditions. |
| Version | Version | A given state of a library item or a project, fixed at a point in time, decisive for both conformity check and library management. See Versioning library content. |