How to register own production from solar panels
Purpose
Section titled “Purpose”Register exported electricity from e.g. solar panels, so it’s subtracted in the calculation.
Prerequisites
Section titled “Prerequisites”You’re on Building and operation, under Energy consumption in operation, and you have the BE18 key figures for the project.
- Read Solceller (photovoltaics) under Ydelse fra særlige kilder in the BE18 key figures.
- Subtract the threshold of 13.2 kWh/m²/year from the yield. If the result is positive,
that is the exported electricity. If it is zero or negative, enter nothing: the entire
production is already included in the energy framework.
Exported electricity=yield from solar panels − 13.2 kWh/m²/year
- Find the electricity row under Energy consumption in operation. If the building does not have an electricity energy source yet, add one.
- Write the calculated amount of exported electricity in the Exported column on the electricity row, in kWh/m²/year. The column can only be filled in on electricity rows.
BE18 has already subtracted the share of renewable energy production that may be included in the energy framework from the key figures for heat and electricity. That share must therefore not be entered again in LCAbyg.
Where the threshold comes from
Section titled “Where the threshold comes from”Renewable energy production may be included in the energy framework by no more than 25 kWh/m²/year (guidance on energy consumption 1.12). That figure carries a factor of 1.9 for electricity production under BR18 § 252, and since LCAbyg needs the actual energy demand without an energy factor, the threshold becomes 25 / 1.9 = 13.2 kWh/m²/year.
Result
Section titled “Result”Exported electricity counts as negative consumption in module D, not in B6. Below the table it is subtracted from Net operational consumption.
See also
Section titled “See also”- Module D in the glossary: reported separately and does not count towards the limit value
- How to add an energy source
- Energy supplements from BE18: where the key figures appear in BE18